LEMONA INDUSTRIAL S.A
This project was carried out for LEMONA INDUSTRIAL S.A and included the design, manufacture, transport, assembly, testing and commissioning of a waste fraction handling facility.
INITEC ENERGÍA
This project was carried out for INITEC ENERGÍA at the Litoral Thermal Power Plant (ENDESA) and included the design, manufacture, transport, assembly, testing and commissioning of a gypsum handling facility.
CIUDEN
This project was carried out for CIUDEN and included the design, manufacture, transportation, assembly, testing and commissioning of a facility for the reception and transportation of forest biomass.
SPBE
The project carried out for SPBE in the Biomass Plant of San Pedro de Macorís (Dominican Republic), included the design, manufacture, supervision of assembly and start-up of the bagasse storage park and feed to the boiler.
GESTAMP
These projects carried out for GESTAMP in Ence's Biomass Power Plants included the design, construction, transportation, assembly, testing and commissioning of slag and fly ash transportation systems.
GESTAMP
These projects carried out for GESTAMP in the Biomass Power Plants built by ELECNOR, in the Portuguese towns of Viseu and Fundão, included the design, construction, transportation, assembly, testing and commissioning of slag and fly ash transportation systems.
GENERAL ELECTRIC
This project was carried out for GENERAL ELECTRIC at the As Pontes Thermal Power Plant (ENDESA) and included the design, construction, transportation and formation of a facility for handling gypsum.
PHB Weserhütte
This project was carried out for PHB Weserhütte at Coal Thermal Power Plant from Kilpilahti (Finland) and included the design, manufacture and Ex-works supply of two silos, with 2,500 m³ capacity, for storage and dosing of coal and asphaltene, equipped with a 60 m³/h rotary extractor system.
PHB Weserhütte
This project was carried out for PHB Weserhütte at the Jorf Lasfar (OCP) plant and comprised the design, manufacture and Ex-works supply of two lime dosing stations, with a storage capacity of 40 m³ and a dosing capacity of up to 2.5 t / h.
Acciona Agua - Besix JV
This project was carried out for Acciona Agua - Besix JV at the Jebal Ali plant (DEWA) in Dubai and included the engineering, manufacturing and supply (Ex-works) of 4 rotary extraction systems for 4 silos of dehydrated sludge, with a storage capacity of 150 m³ and with an extraction capacity of up to 40 m³ / h.